Horace Harding Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Horace Harding Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: January 2025

Construction

Start Date: February 2025
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: $3,013,000
Funding Source: City Council

Location

Horace Harding Playground, Queens
62nd Drive between 97th Place and 98th Street
Community Board: 06

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project