Horace Harding Playground Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct Horace Harding Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
January 2022
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Adjusted Completion
Date:
January 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Horace Harding Playground, Queens
62nd Drive between 97th Place and 98th Street
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024