Detective Keith L. Williams Park Track and Field, Tennis Courts and Playground Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the track, synthetic turf field, tennis courts, and playground at Detective Keith L. Williams Park. The work includes new synthetic turf, new track, bleachers, tennis court pavements, play equipment for 2-5 and 5-12 years old, spray shower, swings, seating areas, security lighting, fencing, drainage, electrical work, water supply and planting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
March 2022
Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Detective Keith L Williams Park, Queens
173rd Street and between 104th Avenue and 106th Avenue
Community Board: 12