Helen Marshall Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a synthetic turf field at Helen Marshall Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: March 2022
Completion Date: September 2023

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Helen Marshall Playground, Queens
100th Street between 24th Avenue and 25th Avenue
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024