Peter Detmold Park Water Service Reconstruction
-
100% complete
-
100% complete
-
95% complete
This project will reconstruct the water service in Peter Detmold Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2020
Projected Completion Date:
December 2021
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
August 2023
Construction
Start Date: December 2023
Projected Completion Date:
December 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Peter Detmold Park, Manhattan
FDR Drive between East 49th Street and East 51st Street
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024