Peter Detmold Park Water Service Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    95% complete

This project will reconstruct the water service in Peter Detmold Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2020
Projected Completion Date: December 2021
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: August 2023

Construction

Start Date: December 2023
Projected Completion Date: December 2024

Understand how we build parks.

Funding

Total Funding: $610,000
Funding Sources:
  • City Council
  • Mayoral

Location

Peter Detmold Park, Manhattan
FDR Drive between East 49th Street and East 51st Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024