Cuyler Gore Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the entrances, playground and passive recreation area at Cuyler Gore Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: July 2024

Construction

Start Date: November 2024
Projected Completion Date: November 2025