Greene Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    57% complete

This project will reconstruct the playground at Greene Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: December 2023

Construction

Start Date: April 2024
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $3,001,000
Funding Source: City Council

Location

Greene Playground, Brooklyn
Greene & Washington Avenues
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025