Russell Pedersen Playground Reconstruction
-
100% complete
-
100% complete
-
49% complete
This project will reconstruct the play area at Russell Pedersen Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2020
Projected Completion Date:
December 2021
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
April 2024
Construction
Start Date: May 2024
Projected Completion Date:
May 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Russell Pedersen Playground, Brooklyn
Colonial Road between 83rd and 85th Streets
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025