Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
May 2021
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
June 2021
Construction
Start Date: September 2021
Projected Completion Date:
May 2022
Completion Date: March 2022