Brooklyn Park Tree Planting FY21 (BG-321M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new and replacement park trees in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: May 2021
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: July 2021

Construction

Start Date: October 2021
Projected Completion Date: June 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $501,000
Funding Source: Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024