Idlewild Park Reforestation FY21
-
100% complete
-
100% complete
-
29% complete
This project will remove invasive species and plant new and replacement trees in Idlewild Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2020
Projected Completion Date:
April 2021
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
December 2022
Construction
Start Date: January 2023
Projected Completion Date:
July 2025
Understand how we build parks.
Funding
Location
Idlewild Park, Queens
Rockaway Boulevard, Brookville Boulevard, 149th Avenue, 150th Road
Community Board: 13
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024