Idlewild Park Reforestation FY21

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    25% complete

This project will remove invasive species and plant new and replacement trees in Idlewild Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2020
Projected Completion Date: April 2021
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: December 2022

Construction

Start Date: January 2023
Projected Completion Date: July 2025

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Idlewild Park, Queens
Rockaway Boulevard, Brookville Boulevard, 149th Avenue, 150th Road
Community Board: 13

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024