Idlewild Park Reforestation FY21
-
100% complete
-
100% complete
-
77% complete
This project will remove invasive species and plant new and replacement trees in Idlewild Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2020
Projected Completion Date:
April 2021
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
December 2022
Construction
Start Date: January 2023
Projected Completion Date:
July 2025
Understand how we build parks.
Funding
Location
Idlewild Park, Queens
Rockaway Boulevard, Brookville Boulevard, 149th Avenue, 150th Road
Community Board: 13
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025