Space Time Playground Synthetic Turf Field and Basketball Courts Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a synthetic turf field and reconstruct two basketball courts at Space Time Playground, including green infrastructure to capture storm water and new trees, benches, fencing, pavements, bleachers, water supply and drainage.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: June 2021
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Space Time Playground, Bronx
Lafayette Avenue between Bolton and Underhill Avenues
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024