Ferry Point Park 9-11 Living Memorial Flagpole Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    75% complete

This project will construct a new flagpole and associated plaza at the 9/11 Living Memorial Grove at Ferry Point Park, including a path for ADA accessibility.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: April 2024

Construction

Start Date: May 2024
Projected Completion Date: May 2025

Understand how we build parks.

Funding

Total Funding: $1,250,000
Funding Source: City Council

Location

Ferry Point Park, Bronx
Hutchinson River Parkway at Ferry Point Park West between the East River and Bronx-Whitestone Bridge
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024