Freshkills Park Owl Hollow Fields Parking and Access Road Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an entry drive and other parking lot improvements at Owl Hollow Fields in Freshkills Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2020
Projected Completion Date:
June 2021
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
July 2022
Construction
Start Date: January 2023
Projected Completion Date:
September 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Arthur Kill Road and Arden Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project