Freshkills Park Owl Hollow Fields Parking and Access Road Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an entry drive and other parking lot improvements at Owl Hollow Fields in Freshkills Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2020
Projected Completion Date: June 2021
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: July 2022

Construction

Start Date: January 2023
Projected Completion Date: September 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $761,000
Funding Source: Mayoral

Location

Freshkills Park, Staten Island
Arthur Kill Road and Arden Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024