Queens Pavement Areas Reconstruction
-
100% complete
-
100% complete
-
48% complete
This project will reconstruct multipurpose play areas at Oakland Gardens, Alley Park, and Hoover-Manton Playground, and the parking lot near Springfield Boulevard and 76th Avenue in Alley Pond Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date:
February 2023
Procurement
Start Date: February 2023
Projected Completion Date:
July 2022
Completion
Date:
August 2024
Construction
Start Date: July 2024
Projected Completion Date:
July 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Alley Park, Queens
67 Avenue & 230 Street
Community Board: 11 -
Alley Pond Park, Queens
Little Neck Bay to Springfield Boulevard, Union Turnpike
Community Board: 11 -
Hoover - Manton Playgrounds, Queens
Manton Street & 83 Avenue
Community Board: 08 -
Oakland Gardens, Queens
E/S Springfield Boulevard & 54 Avenue
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024