Arden Woods Trail Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct hiking trails at Arden Woods.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2020
Projected Completion Date: September 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: June 2022

Construction

Start Date: August 2022
Projected Completion Date: July 2023
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $567,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Arden Woods, Staten Island
Between Arthur Kill Road and Woodrow Road
Community Board: 03

 