Staten Island and Bronx Deer Exclusion Fence Installation
-
100% complete
-
100% complete
-
27% complete
This project will install deer exclusion fence in Staten Island and the Bronx.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2021
Projected Completion Date:
January 2022
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
October 2023
Construction
Start Date: October 2023
Projected Completion Date:
October 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations, Staten Island and the Bronx.
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025