Staten Island and Bronx Deer Exclusion Fence Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    27% complete

This project will install deer exclusion fence in Staten Island and the Bronx.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: October 2023

Construction

Start Date: October 2023
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $730,000
Funding Source: Mayoral