Sherman Creek Water Service Installation
-
100% complete
-
100% complete
-
100% complete
This project will install water service at Sherman Creek.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
March 2017
Completion
Date:
January 2017
Construction
Start Date: February 2018
Projected Completion Date:
March 2018
Completion Date: March 2018
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Sherman Creek, Manhattan
10th Avenue, Dyckman Street, Harlem River Drive
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025