Michaelis-Bayswater Park Public Restroom Building Construction
-
100% complete
-
40% complete
-
0% complete
This project will construct a public restroom building in Michaelis-Bayswater Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
April 2020
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Adjusted Completion
Date:
June 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Bayswater Park, Queens
Beach Channel Drive and Bay 32nd Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024