Kelly Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Kelly Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2019
Projected Completion Date: December 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: January 2023

Construction

Start Date: April 2023
Projected Completion Date: April 2024
Completion Date: July 2024

Understand how we build parks.

Funding

Total Funding: $2,686,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Kelly Park Playground, Brooklyn
Avenue S and East 15th Street
Community Board: 15

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024