Canarsie Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building in Canarsie Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
September 2015
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
January 2018
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
October 2023
Completion Date: October 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- Private
Location
Canarsie Park, Brooklyn
Seaview Avenue and Paerdegat Avenue North
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025