Canarsie Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a public restroom building in Canarsie Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: September 2015
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: January 2022

Construction

Start Date: May 2022
Projected Completion Date: October 2023
Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $4,385,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • Private

Location

Canarsie Park, Brooklyn
Seaview Avenue and Paerdegat Avenue North
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025