Marine Park PS 278 Playground Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the play area and sport courts at PS 278 Playground in Marine Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2021
Adjusted Completion Date:
December 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- State
Location
Marine Park, Brooklyn
Fillmore Avenue and Madison Place
Community Board: 15, 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024