Marine Park PS 278 Playground Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the play area and sport courts at PS 278 Playground in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Adjusted Completion Date: December 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • State

Location

Marine Park, Brooklyn
Fillmore Avenue and Madison Place
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024