Riverside Park Drainage System Reconstruction From 108th to 116th Street
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the drainage system at Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
December 2022
Completion Date:
December 2023
Procurement
Start Date: December 2023
Projected Completion Date:
December 2024
Adjusted Completion
Date:
July 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Riverside Park, Manhattan
Riverside Park from 108th to 116th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024