NYCHA Watson Houses Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct an existing playground in the open space at the Watson Houses, with new play equipment, adult fitness equipment, and safety surfacing, a spray shower, sitting areas, plantings, fencing, pavements, and drinking fountains.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: February 2023

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Source: Mayoral

Location

Watson Houses Playground, Bronx
Colgate Avenue between Watson Avenue and Westchester Avenue
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024