NYCHA Watson Houses Open Space Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct an existing playground in the open space at the Watson Houses, with new play equipment, adult fitness equipment, and safety surfacing, a spray shower, sitting areas, plantings, fencing, pavements, and drinking fountains.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2020
Projected Completion Date:
March 2021
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
February 2023
Construction
Start Date: March 2023
Projected Completion Date:
March 2024
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Watson Houses Playground, Bronx
Colgate Avenue between Watson Avenue and Westchester Avenue
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project