NYCHA Sotomayor Houses Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new open space at the Sotomayor Houses.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: July 2022

Procurement

Start Date: July 2022
Projected Completion Date: April 2023
Completion Date: January 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $1,900,000
Funding Source: Mayoral

Location

Watson Avenue between Taylor Avenue and Thieriot Avenue

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024