NYCHA Kingsborough Houses Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    50% complete

This project will reconstruct two playgrounds in NYCHA Kingsborough Houses.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: September 2023

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $5,100,000
Funding Source: Mayoral

Location

Rochester Avenue, Pacific Street, Buffalo Avenue, Bergen Street.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024