NYCHA Kingsborough Houses Open Space Construction
-
100% complete
-
100% complete
-
82% complete
This project will reconstruct two playgrounds in NYCHA Kingsborough Houses.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
January 2022
Procurement
Start Date: January 2022
Projected Completion Date:
October 2022
Completion
Date:
September 2023
Construction
Start Date: March 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Rochester Avenue, Pacific Street, Buffalo Avenue, Bergen Street.
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025