Poe Cottage Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will reconstruct the historic wood shingle roof and associated systems at Poe Cottage.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: October 2022

Procurement

Start Date: October 2022
Projected Completion Date: July 2023
Completion Date: April 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $964,000
Funding Sources:
  • Borough President
  • City Council

Location

Poe Park, Bronx
2640 Grand Concourse
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025