Captain Dermody Triangle Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Captain Dermody Triangle.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date:
September 2021
Procurement
Start Date: September 2021
Projected Completion Date:
June 2022
Completion
Date:
January 2023
Construction
Start Date: March 2023
Projected Completion Date:
March 2024
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Source: State
Location
Captain Dermody Triangle, Queens
48th Avenue and 216th Street
Community Board: 11
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025