Flushing Meadows Corona Park Aquatic Center Ice Rink Chiller Plant Replacement

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will replace the chiller plant for the ice skating rink at Flushing Meadows Corona Park Aquatic Center.

Project Notes

Project Update: Parks is continuing to develop the documents to build this project.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: October 2023

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024