Michaelis-Bayswater Park Maintenance and Operations Building Construction
-
100% complete
-
40% complete
-
0% complete
This project will construct a maintenance and operations building in Michaelis-Bayswater Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
April 2020
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Adjusted Completion
Date:
October 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Bayswater Park, Queens
Bay 32nd Street and Dwight Avenue
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024