Michaelis-Bayswater Park Maintenance and Operations Building Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct a maintenance and operations building in Michaelis-Bayswater Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: April 2020
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Adjusted Completion Date: October 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Federal
  • Mayoral

Location

Bayswater Park, Queens
Bay 32nd Street and Dwight Avenue
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024