Michaelis-Bayswater Park Maintenance and Operations Building Construction
-
80% complete
-
0% complete
-
0% complete
This project will construct a maintenance and operations building in Michaelis-Bayswater Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
April 2020
Adjusted Completion Date:
January 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Bayswater Park, Queens
Bay 32nd Street and Dwight Avenue
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025