Michaelis-Bayswater Park Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Michaelis-Bayswater Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: April 2020
Completion Date: October 2022

Procurement

Start Date: October 2022
Projected Completion Date: July 2023
Adjusted Completion Date: January 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Bayswater Park, Queens
Beach Channel Drive, Bay 32nd Street, Norton Avenue
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024