Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation
-
100% complete
-
100% complete
-
100% complete
This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2019
Projected Completion Date:
December 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
February 2021
Construction
Start Date: February 2020
Projected Completion Date:
March 2020
Completion Date: July 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project