Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: February 2021

Construction

Start Date: February 2020
Projected Completion Date: March 2020
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $2,434,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project