Tappen Park Village Hall Roof Reconstruction
-
100% complete
-
100% complete
-
64% complete
This project will reconstruct the roof at the Village Hall located in Tappen Park. The work will include replacing or resetting slate roof tiles and chimney bricks; new gutters, skylights, flashing, and an access hatch; and repairing the dormer windows.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
August 2021
Completion
Date:
July 2023
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Tappen Park, Staten Island
111 Canal Street
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project