Tappen Park Village Hall Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    64% complete

This project will reconstruct the roof at the Village Hall located in Tappen Park. The work will include replacing or resetting slate roof tiles and chimney bricks; new gutters, skylights, flashing, and an access hatch; and repairing the dormer windows.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Completion Date: July 2023

Construction

Start Date: October 2023
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $5,500,000
Funding Source: Mayoral

Location

Tappen Park, Staten Island
111 Canal Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025