Tappen Park Village Hall Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    41% complete

This project will reconstruct the roof at the Village Hall located in Tappen Park. The work will include replacing or resetting slate roof tiles and chimney bricks; new gutters, skylights, flashing, and an access hatch; and repairing the dormer windows.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Completion Date: July 2023

Construction

Start Date: October 2023
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $5,500,000
Funding Source: Mayoral

Location

Tappen Park, Staten Island
111 Canal Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024