Tappen Park Village Hall Roof Reconstruction
-
100% complete
-
100% complete
-
50% complete
This project will reconstruct the roof at the Village Hall located in Tappen Park. The work will include replacing or resetting slate roof tiles and chimney bricks; new gutters, skylights, flashing, and an access hatch; and repairing the dormer windows.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
August 2021
Completion
Date:
July 2023
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Tappen Park, Staten Island
111 Canal Street
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024