College Point Fields Sports and Security Lighting Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct sports and security lighting at College Point Fields.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: November 2021
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: April 2023

Construction

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $2,400,000
Funding Sources:
  • Borough President
  • City Council

Location

College Point Fields, Queens
130th Street between 23rd Avenue and 26th Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project