Children's Magical Garden Water Service Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct water service at Children's Magical Garden.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2019
Projected Completion Date:
December 2020
Completion Date:
January 2021
Procurement
Start Date: January 2021
Projected Completion Date:
October 2021
Completion
Date:
March 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: City Council
Location
Norfolk Street and Stanton Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024