Red Hook Community Farm Water Service Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct water service at Red Hook Community Farm.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: October 2021
Completion Date: August 2022

Construction

Start Date: September 2022
Projected Completion Date: March 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $564,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Red Hook Recreation Area, Brooklyn
Columbia Street and Halleck Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025