6BC Botanical Garden Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install water service at 6BC Botanical Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: March 2024

Construction

Start Date: May 2024
Projected Completion Date: May 2025
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $263,000
Funding Sources:
  • City Council
  • Mayoral

Location

East 6th Street between Avenue B and Avenue C

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024