Bronx Park Skate Park Drinking Fountain Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct water service and a drinking fountain at the skate park in Bronx Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: October 2021
Completion Date: March 2023

Construction

Start Date: May 2023
Projected Completion Date: November 2023
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $338,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bronx Park, Bronx
Bronx Park East between Britton Avenue and Arnow Avenue
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project