Bronx Park Skate Park Drinking Fountain Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct water service and a drinking fountain at the skate park in Bronx Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2021
Completion Date:
February 2021
Procurement
Start Date: February 2021
Projected Completion Date:
October 2021
Completion
Date:
March 2023
Construction
Start Date: May 2023
Projected Completion Date:
November 2023
Completion Date: November 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Bronx Park, Bronx
Bronx Park East between Britton Avenue and Arnow Avenue
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024