Greenbelt Recreation Center Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field, rain garden and will install new field lighting at Greenbelt Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
January 2022
Completion
Date:
June 2023
Construction
Start Date: August 2023
Projected Completion Date:
August 2024
Completion Date: November 2024
Understand how we build parks.
Funding
Funding Source: City Council
Location
Blood Root Valley, Staten Island
Brielle Avenue between Rockland Avenue and Walcott Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024