Manhattan Beach Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    44% complete

This project will reconstruct the tennis courts at Manhattan Beach Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: July 2022

Procurement

Start Date: July 2022
Projected Completion Date: April 2023
Completion Date: March 2024

Construction

Start Date: April 2024
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $3,800,000
Funding Source: City Council

Location

Manhattan Beach Park, Brooklyn
Oriental Boulevard at Mackenzie Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024