Manhattan Beach Park Tennis Courts Reconstruction
-
100% complete
-
100% complete
-
54% complete
This project will reconstruct the tennis courts at Manhattan Beach Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date:
July 2022
Procurement
Start Date: July 2022
Projected Completion Date:
April 2023
Completion
Date:
March 2024
Construction
Start Date: April 2024
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Manhattan Beach Park, Brooklyn
Oriental Boulevard at Mackenzie Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024