Shore Park and Parkway Dog Run Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a dog run in Shore Park and Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
June 2022
Construction
Start Date: July 2022
Projected Completion Date:
July 2023
Completion Date: August 2023