Astoria Park Great Lawn Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the landscape in Astoria Park north of the pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: September 2022

Procurement

Start Date: September 2022
Projected Completion Date: June 2023
Completion Date: September 2024

Construction

Start Date: September 2024
Projected Completion Date: December 2025

Understand how we build parks.

Funding

Total Funding: $6,384,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Astoria Park, Queens
Shore Boulevard, 19th Street, 22nd Drive, 23rd Road
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024