Astoria Park Great Lawn Pathways Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the landscape in Astoria Park north of the pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2021
Projected Completion Date:
June 2022
Completion Date:
September 2022
Procurement
Start Date: September 2022
Projected Completion Date:
June 2023
Completion
Date:
September 2024
Construction
Start Date: September 2024
Projected Completion Date:
December 2025