Lt. Michael R. Davidson Playground Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct Lt. Michael R. Davidson Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2020
Projected Completion Date: December 2021
Completion Date: August 2022

Procurement

Start Date: August 2022
Projected Completion Date: May 2023
Completion Date: January 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $4,815,000
Funding Source: City Council

Location

Lt. Michael R. Davidson Playground, Queens
50th Street and 39th Avenue
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 02/21/2025