Oakland Lake Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will reconstruct pathways at Oakland Lake in Alley Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2020
Projected Completion Date: June 2021
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: August 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $416,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Alley Pond Park, Queens
Springfield Boulevard, 46th Avenue, Garland Drive, 56th Avenue
Community Board: 11

 

Project Staff

Project Liaison: Meira Berkower