Oakland Lake Pathways Reconstruction
-
100% complete
-
100% complete
-
98% complete
This project will reconstruct pathways at Oakland Lake in Alley Pond Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2020
Projected Completion Date:
June 2021
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Completion
Date:
August 2024
Construction
Start Date: September 2024
Projected Completion Date:
September 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Alley Pond Park, Queens
Springfield Boulevard, 46th Avenue, Garland Drive, 56th Avenue
Community Board: 11
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024