Oakland Lake Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will reconstruct pathways at Oakland Lake in Alley Pond Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2020
Projected Completion Date: June 2021
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: August 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $416,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Alley Pond Park, Queens
Springfield Boulevard, 46th Avenue, Garland Drive, 56th Avenue
Community Board: 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025