Frisch Field Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct the natural turf baseball field at Frisch Field, including grading, drainage, benches, fencing, dugouts, sidewalks, pathways, drinking fountains and bottle fillers.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
February 2022
Adjusted Completion Date:
October 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Mosholu Parkway, Bronx
Mosholu Parkway and Webster Avenue
Community Board: 07, 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024