A. Philip Randolph Square Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct A. Philip Randolph Square and adjacent sidewalks and intersections.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: October 2024
Projected Completion Date: April 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

A Philip Randolph Square, Manhattan
Adam Clayton Powell Jr. Boulevard, St. Nicholas Avenue, West 117th Street
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025