Queensbridge Baby Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    12% complete

This project will reconstruct Queensbridge Baby Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: May 2023
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: September 2024

Construction

Start Date: September 2024
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Queensbridge Park, Queens
North of Queensboro Bridge between Vernon Boulevard and 21st Street
Community Board: 01, 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025