Queensbridge Baby Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Queensbridge Baby Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: May 2023
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: September 2024

Construction

Start Date: September 2024
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Queensbridge Park, Queens
North of Queensboro Bridge between Vernon Boulevard and 21st Street
Community Board: 01, 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024