Court Square Park Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct Court Square Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: September 2022

Procurement

Start Date: September 2022
Projected Completion Date: May 2023
Adjusted Completion Date: August 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Court Square Park, Queens
Jackson Avenue, Court Square West, Thomson Avenue
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024