West 186th Street Basketball Court Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct West 186th Street Basketball Court.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
June 2023
Completion Date:
December 2023
Procurement
Start Date: December 2023
Projected Completion Date:
December 2024
Adjusted Completion
Date:
February 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
West 186th Street Basketball Court, Manhattan
West 186th Street between Audubon and St. Nicholas Avenues
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024