Woodlawn Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Woodlawn Playground in Van Cortlandt Park, including new steel play equipment, swings, safety surfacing, fencing, landscaping, benches, and park security lighting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Van Cortlandt Park, Bronx
Van Cortlandt Park East between Oneida and Kepler Avenues
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024