Bennett Park Central Lawn Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will reconstruct the central lawn in Bennett Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: May 2023

Procurement

Start Date: May 2023
Projected Completion Date: August 2022
Completion Date: February 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $1,100,000
Funding Sources:
  • Borough President
  • City Council

Location

Bennett Park, Manhattan
West 183rd Street between Pinehurst Avenue and Fort Washington Avenue
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024