Bennett Park Central Lawn Reconstruction
-
100% complete
-
100% complete
-
95% complete
This project will reconstruct the central lawn in Bennett Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
May 2023
Procurement
Start Date: May 2023
Projected Completion Date:
August 2022
Completion
Date:
February 2024
Construction
Start Date: March 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Bennett Park, Manhattan
West 183rd Street between Pinehurst Avenue and Fort Washington Avenue
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project